Retention bond
Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate that is retained by the client. The purpose of retention is to ensure the contractor properly completes the works required under the contract.
Half of the amount retained is released on certification of practical completion and the remainder is released upon certification of making good defects. Retention due to subcontractors may in turn be held by the main contractor and so on down through the contractual chain.
The recovery of retention is often a difficult area for parties in the contractual chain and cash flow problems frequently arise resulting from non-payment. In theory, this should be prevented by the Housing Grants Construction and Regeneration Act which disallows ‘pay when paid’ clauses, however, retention is commonly not released on time or in accordance with the contract. For subcontractors in particular, the release of retention may rely on circumstances outside of their contract or their control, for example, defects being remedied under the main contract by other parties.
Retention bonds are way of avoiding problems associated with retention recovery. Amounts that would otherwise have been held as retention are instead paid, with a bond being provided to secure the amount. Similar to retention, the bond’s value will usually reduce after the certification of practical completion.
Only if practical completion is not achieved by the subcontractor or if they prevent a certificate of making good defects from being issued will the retention bond take effect. The contractor is then able to ‘call’ on the retention bond.
A subcontractor is usually allowed a fixed period of time to rectify any defects, and this is stipulated by the retention bond. Should they fail to rectify the defect, the retention bond can be called on by the contractor and the surety must cover the remedial costs, before then pursuing the subcontractor.
Whilst subcontractors must pay the surety’s premiums, the benefit to them is that they do not have to chase retention monies post-completion, and no retention monies will be withheld. This cash flow security is often seen as worth the cost of the premium. Similarly, retention bonds are advantageous to contractors in improving the cash flow and financial stability of the subcontractor, making them less likely to default on the works.
Retention bonds include a fixed expiry date, making it clear when the subcontractor is released from its obligations.
Retention bonds may also be used as an alternative to retention between the employer and the main contractor.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bonds and guarantees (Aviva Insurance Limited v Hackney Empire Limited 2012).
- Bonds in construction contracts.
- Campaign for cash retentions reform.
- Certificate of making good defects.
- Construction (Retention Deposit Schemes) Bill 2017-19.
- Defects.
- Defects liability period.
- Final account.
- Holdback.
- Parent company guarantee.
- Performance bond.
- Practical completion.
- Retainage.
- Retention.
- Retention held in trust fund.
- Sub-contractor.
- The problems with retention.
- Zero-coupon bond.
[edit] External references
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.